Work on the Tarbela 5th Extension Hydropower Project has been stopped indefinitely after water rushed into Tunnel Five on Monday, November 9, 2026. Haripur Deputy Commissioner Waseem Ahmed said a protective barrier, or bund, gave way and let the water in.
All Pakistani and foreign workers were moved to safety. One Pakistani worker was swept away by the water but was pulled out by rescue teams. No deaths were reported.
WAPDA’s side of the story
The Water and Power Development Authority (WAPDA), which is building the project, gave a slightly different account. It said weak rock collapsed while workers were digging in the tunnel that connects the water intake to the powerhouse. Water from the intake pit then flowed into the tunnel and the powerhouse area.
WAPDA said the water has been fully drained and no more is entering the work sites. It also rejected viral claims that Tunnel Five had collapsed. The main tunnel, the unfinished powerhouse and the switchyard were not damaged, the authority said.
Waseem Ahmed said a high-level inquiry will check whether a weak structure or a technical fault caused the failure. The next steps will be decided after its report. According to sources quoted by PhotoNews Pakistan, the federal government wants the inquiry finished within a week, and the Prime Minister’s Office has shown serious concern.
Second failure this year
This is not the project’s first collapse. Earlier, a temporary wall that holds back water downstream, called a cofferdam, broke at the same site.
A government inquiry found that collapse was not caused by floods. It blamed a change in the wall’s design to a weaker rock-filled type, along with poor supervision, according to the Planning Commission. In July, reports said the inquiry held WAPDA, the Chinese contractor and the consultant responsible.
Cost has nearly quadrupled
The project was first estimated at Rs. 82 billion. By May 2026, the Planning Commission put its cost at Rs. 316.4 billion, almost four times as much. That earlier collapse also pushed the work back by about two years, Profit reported.
The Planning Commission also warned that power from the project could cost about Rs. 28 per unit to produce, making it hard to justify financially. Any fresh delay or repair bill could add to that.
The World Bank is lending $390 million and the Asian Infrastructure Investment Bank $300 million. China’s Power Construction Corporation is doing the main building work.
Why it matters for power supply
The project is being built on Tunnel Five of Tarbela Dam, Pakistan’s largest water reservoir. It will add 1,530 megawatts through three units of 510MW each. That would raise Tarbela’s total capacity from 4,888MW to 6,418MW.
The government had listed all three units for start-up between September and December 2026 in its power plan for this year. Those dates had already slipped, and Monday’s flooding could push them back further.